11.13.2007

Surveying the River Bed


Brian, a new friend to the project, was brave enough to volunteer to be the rod man on the day we had to survey the river bed for the group back in New York. He told us he wasn't worried about leach bites but we were all glad to see he didn't have any friends attached when he got out of the river.


In additional to helping EWB obtain some valuable data Brian was also afternoon entertainment for some of the local villagers.

Site Logistics


The Cambodian dry season is only five months long, from about November to March. So we decided to begin construction November 1st to give ourselves the longest time possible in case of delays or other issues. However, the river flow is still at its highest right now so we had to come up with a solution for crossing the river with our heavy construction equipment. Narith proposed installing a concrete culvert as a temporary river crossing.


It took about two and a half days to set the culverts, place the soil on top and divert the stream but our new path across the river works very well and the equipment has had no problems crossing.

11.09.2007

JETS


Shannon Flanagan and Christina Ho of the EWB New York Chapter have been working very hard to create an Educational Outreach arm for the chapter. One of their recent initiatives was to collaborate with the Junior Engineering Technical Society or JETS to create lesson plans based on an EWB Project and they were nice enough to use the Cambodia project for their first project! They did a pretty amazing job and it's really interesting to check out the lesson plans.

11.07.2007

Community Meeting


We had a community meeting at Trau Kod with HRND and some of the commune and village leaders last weekend. Human Translation and HRND wanted to let the community know that we are starting construction and we intend to finish before the next rainy season.


There are still quite a few community issues such as the Water User Group, land merchants from Siem Reap purchasing land within the reservoir basin and a farmer still living on the embankment so we also tried to let everyone know that this is a community project and we are only here to help facilitate resolutions to the issues. We are not here to make decisions for the community. The general tone of the meeting seemed positive although 99% of it was spoken in Khmer so it was tough to tell. For the most part, Tobias and I just tried to look interested and then laugh when it appeared a funny joke had been told.

11.03.2007

Construction Has Begun!


The equipment finally made it to the site and the embankment repair work has begun! The bulldozer will be working on vegetation clearing and erosion damage removal for the next few days but next week we will begin placing and compacting soil.


This is a photo of the site office being constructed. Work will be taking place from 7:00am to 5:00pm, 7 days a week so we are going to try and make things a bit more comfortable.

The Road to Trau Kod


Last Thursday we began moving the equipment to Trau Kod. It takes a little over an hour to get to the site from Siem Reap and that is due, in large part, to the last 5km of dirt road through Kroper Village. So our plan was to unload the equipment from their tailors and repair the road as we went so the concrete trucks will have an easier time traveling to the site. The majority of the repair work was just filling holes and moving vegetation that has encroached on the road. However, there was one wood bridge that was completely unsuitable for heaving equipment.


So Narith directed the equipment operators to demolish the wood bridge, back fill soil into the river, dig a trench, and install a concrete culvert.


The photograph above is of the audience that came to watch the bridge demolition and culvert installation. It was quite an operation but the villagers seemed very excited about the improvement to their road.

10.31.2007

Villager Construction Taining


Last week I attended one of Narith's construction training sessions. Narith has been providing construction training to members of all of the Balang commune villages interested in working on the Trau Kod project since the beginning of the rainy season. The session was held in a small building next to the Balang Police Station where we met with the Commune Chief and the Prom Kod Chief, the man that hosted us when we stayed over night in village on our last trip.


The villagers in attendance that day were "group leaders" or foremen that will be in charge of small groups. Narith's sessions have reviewed the project scope, the project location, construction safety, construction techniques, etc. Most have had experience working as carpenters and masons in Siem Reap and seemed rather bored with Narith's lesson but the benefits of these sessions will probably be very valuable for the group and for the project when we start construction tomorrow.

10.29.2007

they came, they saw, ....they supported

picassa photos
thanks to Maria and Linda for their tremendous efforts in organizing the bar night fundraiser event. friends and colleagues came and supported, helping raise over $1100! with a match from the PB Foundation, that brings us to over $2200! linda and maria
thank you all for your support!

10.26.2007

Back to Trau Kod


After traveling for what felt like a week, I finally was able to go back to the site Thursday morning with Chai and Narith. We spent almost every day at Trau Kod on our last trip but seeing the size of the embankment and future reservoir basin again still amazed me. I also saw my first leach in the O Ta Bet river which was kind of terrifying.

The plan is start moving the heavy equipment back to the site next week, begin the embankment repair the following week then the water gate in about a month. There is a lot of work to be done but I think everyone is excited to begin.

10.18.2007

bar night: the return

Last year, around this time, we held our first bar night fundraising event. The event was both fun and successful, as many of our friends and colleagues helped us raise about $1600, and with a generous match from the PB Foundation, that totaled $3200! It was a great kickoff event for the project! Join us, nearly 1-1/2 years later, to celebrate and learn of the progress we've made.

Location:
Underground, 613 2nd Ave (btw 33rd & 34th)

When:
Thursday, Oct-25-2007

Suggested Donation:
$10 Students/$15 Everyone Else
(INCLUDES 1 FREE DRINK)

Spread the word!

10.10.2007

Heading Back


Today is my last day in New York! I'm heading back to Siem Reap for a few months to help start up construction. In the past couple of weeks I've been spending a lot of time with friends, eating a lot of pizza and trying to enjoy the city before leaving. It's certainly exciting to be going back and it's really excited that we are getting so close to construction but I'm going to miss New York.

10.02.2007

topo














Every little information helps. One can quickly see how impossible it is to survey every square inch of a 160 acre open field (not to mention, the danger of potential landmines). But after compiling all of the any little surveying that has been done, the hydro team was able to produce a projected topography map using AutoCadd. Ryan spent the weekend shading in the proposed embankment location (solid orange), the estimated water elevation (light blue shade), and the elevation during a 100 year storm (blue hatch).

9.29.2007

Rebar Demonstration










More feedback from the pros. We took a site visit to get a raw taste of how rebars are worked on site. Additionally, we asked questions about formworks and concrete pouring. It was interesting to see how the site was arranged in an "assembly line" manner, where one area would be stationed as the rebar cutting, bending, and labeling area. Another area would be cage making, which consists of laying out the rebars, tick marking them, and tying them together. The cages are stacked aside until they are ready for the next, and final station, which is at the location of the pour. This "assembly line" optimizes the routine and enables the contractors to pour a floor slab every 2 days.


Skanska Meeting


Last Thursday after work we took the 7 train out to Shea Stadium where Jess and Tim picked us up and took everyone to the Skanska office where we met with two Skanska executives to discuss construction logistics for our project. It turned out to be a really great meeting. Vince and Shelly have been working in engineering and construction for many years, Vince actually has experience building in Vietnam, so their review of the project was a good reality check. Some of the points they made were:

1. It is a lot easier to plan and design here in an air-conditioned office than out in the field.
2. K.I.S.S.
3. We need to start getting much more organized in our preparation and planning for construction.

In addition to these themes, they provided us with many ideas and suggestions for building using low-tech methods that can be very effective but are no longer used here in the U.S. It sounded like everyone felt the meeting was extremely valuable despite the fact we all got lost on the way back to the 7 train.

9.09.2007

Labyrinth Spillway Part 2


We have been doing more research on the Labyrinth Spillway and it appears that this could be the most cost effective solution to the auxiliary spillway issue.

Brent is looking into the hydraulics of this spillway type, Ryan put together this preliminary design and Jessica will be working on estimating the costs of this configuration and the traditional spillway and water gate.

9.04.2007

Labyrinth Spillway


When the Hydro team finished their study we realized the water gate auxiliary spillway would not be large enough to handle a 100 year flood. Our investigation has shown that the previous failures were due to over-topping so having a adequately sized spillway is certainly a critical aspect of the design. However, when we began looking into typical spillway designs we realized the costs could be much larger than what we have available.

Then Ryan found the Labyrinth Spillway. The idea is that the effective length of the spillway is increased by using a series of trapezoidal or triangular walls instead of a straight wall. This will increase the cost of the water gate but we will save the cost of building an entirely different spillway. There are also potential savings on future maintenance. We are still discussing whether or not this option will be used but it is an interesting idea.

8.31.2007

TAC Approved


About a month ago we presented our design to the Engineers Without Borders Technical Advisory Committee (TAC) and since then we have been working with them to satisfy their questions and concerns. Early this morning we received our approval! With Human Translations successful fundraiser and this approval we are cleared to begin construction in November when the dry season begins.

8.18.2007

Human Translation Benefit Concert


Last night Human Translation held a Benefit Concert to raise money for our project and it turned out to be a huge success. We had been increasingly concerned with budget issues as the scope of this project has seemed to grow over the last year. This Benefit Concert was expected to be the largest funding source for this project but I think we were all a little skeptical of the outcome. So for HT to have such a successful event is very exciting and will be a huge help for the project.

Congratulations to Human Translation on all of their hard work putting this great event together!

8.16.2007

TAC Review



We submitted our design to the National chapter last month and now we are going through the Technical Advisory Committee (TAC) approval process. The National chapter provides a PowerPoint presentation outline that project teams fill out then present to the TAC. However, our project is a bit larger than the average EWB project so compressing the design into a 20 minute presentation did not really do it justice. The TAC has requested more Geotechnical information so we are creating a response that will answer their questions and hopefully demonstrate that our understanding of the project is much greater than that shown in the short presentation.

7.23.2007

The Design is Done!



We just submitted the project design to EWB National for approval! There is still a ton of detailing and planning work to be done but this was a huge milestone for the design team.

7.15.2007

Mean Someth

This video was taken during a meeting with Mean Someth. Someth was describing the benefits of the water gate project.

Cows on the Embankment

This is a short video of children herding cows back to the village at the end of the day.

Chai (Yin Yah)

This is Chai singing a Khmer song as we walked back to the car after surveying the North side of the reservoir basin. Chai is a 24 year old Civil Engineering student in Siem Reap. With his understanding of the local culture and his ability to quickly pick up new concepts he has been a huge help on the project.

Matt's Snack Attack

On one of our trips to the market we found this cart with pigeons, worms and cicada. I wanted to keep walking but Matt insisted that we try a gigantic, fried cicada. It tasted like pumpkin seeds.

7.01.2007

Design Update

Like many other projects, the lack of time and information is forcing the design team to come up with innovative solutions so the design can proceed. In the ideal case, the Hydro team would have a detailed topographic map of the entire area. This would include clearly defined rivers in the supply area, contours within the reservoir, locations of canals and detailed land use within the demand area. Unfortunately, the only topographic map of the area we have been able to obtain is so rough that our entire reservoir falls between contour lines.
To work around this lack of information, we asked Human Translation to again send their team to the site for an additional survey. This time we requested an approximate "Mud Line" survey and a survey along the 40m contour line. The Mud Line survey roughly followed the elevation where our reservoir water line will be. The survey points along the 40m contour line is needed to correlate the existing topographic map with all of the surveys we have performed. These surveys, combined with the rest of the data already collected will be used to approximate the missing detailed topo map of the area. With this information the Hydro team will be able to complete their model.Ideally, the Concrete team would be able to wait for the Hydo team to complete their study and provide the height necessary for the water gate's emergency overflow. However, we again must make conservative approximations so we can move forward now and then revise our results later. The Cambodian Hydrological Engineer, Yin Savaan, provided Human Translation with a concrete water gate design for this project so our strategy is to merely check this design; not create a new one. This process is just beginning but one initial design modification is to eliminate the footings shown in Yin's drawing (top) for a mat foundation (bottom). Other modifications will include changing the wing-walls slope to match our 3:1 embankment slope, increasing the emergency overflow space, and eliminating the soil-filled ballast for a concrete slab.

It's certainly busy with all of this design work happening simultaneously but the pieces are starting to fit together and it is becoming easier to envision the gate being built.

6.16.2007

River Intersection

As our design progresses we continue to realize that there are gaps in our information. Fortunately, the guys at Human Translation have been ready and willing to help. An example of this situation was when the Hydro Team found a potential river intersection approximately 6km up stream from the Trau Kod reservoir. Depending on the water flow at this intersection the catchment area could be doubled so this intersection has a huge impact on the hydrological analysis. wiL put together the image above to help explain the location to HT. The Australia shaped body of water on the left is our future reservoir and the orange star on the right is the potential river intersection.
We provided GPS points and tried to explain the approximate location very clearly, however, it took three trips to the area for HT to find the intersection. This was certainly not due to a lack of effort. As you can see from the image of the river intersection above it is extremely difficult to survey areas with the heavy vegetation, conflicting local reports and potential land mines.

Despite all of the difficulties, HT was able to send us this sketch explaining this complicated river intersection and our hydrological analysis has been able to continue.

6.05.2007

WUG

Lately, we have been focused on our design deadlines but the importance of the reservoir Water User Group (WUG) keeps coming up as an extremely important aspect of this project. The main goal of our efforts is to build lasting irrigation infrastructure for the Balang Commune. However, the long term effects of our conservative design, the detailed QA/QC procedures and construction oversight may still be greatly diminished if local leaders, as shown in Tobias' photos, do not understand the importance of regular maintenance and a fair water distribution plan.
There appears to be many reports regarding water management in developing countries; each with very specific plans of action. But, from what we have heard, these plans have not often been successfully implemented. Rather, finding strong local leaders within the community is the key for a successful WUG.

5.24.2007

Steve Forbes Visit

l to r: tim, ryan, matt, steve, maria

Steve Forbes, our mentor, came for another visit to NYC a few days ago while enroute to Ghana. To keep with the theme, we had dinner at Kampuchea, a new Cambodian fusion restaurant in the East Village. While chowing on noodles, crepes, and Vietnamese sandwiches, Steve updates us on his insight on finances for this project, "...well, on the bad side, we're short....and on the good side, well, we're short...".

Not exactly the best taste to add to the delicious food, but we've been anticipating this situation, and have given alot of considerations towards value engineering, along with possible fundraising, to help mediate the cost of the project.

5.17.2007

Preparing for the Rainy Season

Tobias just sent us some photos from the site. They have organized between 20 and 40 local villagers a day from the different Balang Commune villages to come work on installing sod on the repaired embankment. This type of community involvement is really great. They are only able to complete about 10m or sod a day so it is slow going but the people that will directly benefit from this project are investing their sweat equity into the repair.

At the same time, we hope the villagers will understand that the reason they are spreading sod is to prevent erosion. You can see in the photo above how much damage was done to the unprotected embankment in just the first two weeks of the rainy season.

5.15.2007

Kite Aerial Photography (KAP)



During the recent site visit, wiL had a chance to try out his Kite Aerial Photography unit (KAP). After converting his apartment into a makeshift shop, he fabricated some mounting hardware and remote controlled servo motors, and mounted his digital camera to a kite. When he got to the dam site, he launched the kite a few hundred feet into the air, and used the remote control to snap off some cool photos of the earthen dam (with construction in progress).



Prior to launching the KAP unit, we had no reliable maps and no legible satellite imagery. The KAP was an inexpensive improvisation that allowed us to quickly obtain reliable data. We'll use the photos (along with our conventional survey data) to more closely define the project scope, perform a hydrological study, and hopefully reduce overall project costs.

5.06.2007

Back to the Office

We are back from Cambodia and straight into the offices of New York. Here are some of the issues we are currently discussing:

1. Value Engineering
2. Hydrological analysis
3. Locating the North and South Embankments
4. Designing the concrete Water Gate
5. Planning the next phases of construction (scheduling, local labor coordination, bidding process)

Being stuck in an office for, what seems like, days on end is not nearly as fun as running around the site in Cambodia but it is great to be back in New York with the rest of the group. We have a huge amount of work to complete before 7/22/07 but I'm confident we will succeed.

5.01.2007

Spotlight: Narith



Sometimes, people come along in life that surprise you with their abilities. You probably know a consultant who's a closet painter; maybe an advertising desk jockey training for a marathon; and let's not forget about your new intern who is much better at your job than you are. Meet Narith: field engineer for our project, and all-around nice guy.


We first met Narith at the site, where he was diligently engaged in something other than what we needed him to do. This moment expressed a more general challenge with the project - how to persuade a group of people, to whom we were total outsiders, that the methods they've been using all their lives are flawed at best, possibly even dangerous. How do you tell a crew of native-born construction workers and engineers, through a language barrier, that a pack of post-pubescent kids who grew up listening to 2 Live Crew knows embankment construction better than anyone else around? It wasn't the easiest thing we've done.


We all came to Cambodia having cut our teeth on the New York City design and construction scene, where showing up to a meeting without your guns drawn means you'll be serving coffee to the big Italian contractor for the remainder of the project. But there's a different feel in Southeast Asia - rather than fight you, these people would rather be your friends. Only a few days after our first meeting, our team was sharing a hot-pot with Narith and his wife at a local barbeque restaurant - a few days later, we began to introduce some of our methods, and found them gradually breaking through the language barrier and into Narith's project routine.


By the end of the trip, it became clear that Narith had a burning desire for us to leave behind our level, the piece of equipment he is shown holding. While we would normally return with any equipment we brought with us, his winning combination of Khmer charisma and gravity-defying mole hair (So Pheap: "It's lucky!") eventually won us over. To this day, Narith remains our eyes and ears in the field; our project, with all the bumps along the way, is certainly fortunate to have him.