The earth work is complete! We finished the all of the major earth moving necessary for the embankment repair and the equipment has been removed from the site. Above is the main embankment ...
the North embankment ...
and the South embankment.
We still have a lot of work, most critical right now is grassing the entire embankment before the rainy season begins. We will also need to install a rip rap band at the future water level, install monitoring wells and potentially a toe drain on the down stream side. But this is a major milestone completed a month before originally scheduled!