11.13.2007

Site Logistics


The Cambodian dry season is only five months long, from about November to March. So we decided to begin construction November 1st to give ourselves the longest time possible in case of delays or other issues. However, the river flow is still at its highest right now so we had to come up with a solution for crossing the river with our heavy construction equipment. Narith proposed installing a concrete culvert as a temporary river crossing.


It took about two and a half days to set the culverts, place the soil on top and divert the stream but our new path across the river works very well and the equipment has had no problems crossing.

No comments: