During the past few meetings, we've been revisting the hydro study done last summer by Brent, Tim, and John. The original study was based on the watergate to provide a spillway capacity large enough to accomodate for a 100yr design storm event. This assumption, however, resulted in a rather costly labyrinth structure. Thus, we decided to modify upon an existing design, and propose to revisit the hydro analysis to consider some spillway capacity that may be provided at other locations, such as the several existing south canals.
Looking back, the hydro assessment have undergone a long journey, starting from getting information about the river intersection, assessing the condition of the south embankment and the entryway of the south canals, and walking down one of the canals, called the Krapeu Canal.